Altius continues to make progress with the logistics project for the cement plant in Potosí (Bolivia), a project for which they have been contracted by Sacyr Industrial. The project started in January 2018 with the first container shipments.
In addition to containerized cargo, Altius is also responsible for the coordination of the onshore part of the project cargo (8 shipments unloaded and delivered, and one shipment in maritime transit), which includes assistance for unloading in Arica (Chile) and transportation to the construction site (where a person must travel to the site to receive documentation and manage drivers for proper unloading). So far, the progress of the project can be summarized as follows:
- Breakbulk cargo: 9 shipments/ 360 packages/ 3.650 T / 19.000 CBM
- FCL cargo: 322 containers (619 TEUs)